Select Page

PSQWAT-11 Water Meter – Relocate Cut Concrete

We recently identified that the water meter on site requires relocating.   We will carry out the following: * Excavate around the inlet of the existing water meter, Cutting concrete with road saw and jack hammer. * Expose and prepare the inlet service. * Isolate...

PSQWAT-10 Water Meter – Relocate

We recently identified that the water meter on site requires relocating.   We will carry out the following: * Excavate around the inlet of the existing water meter * Expose and prepare the inlet service. * Isolate main water pipe for the house.  (Note: Pipework...

PSHWS-49 Hot Water Service – Relocate

Please note: Whilst installing the new heater we were asked to install it in a new location.  We are required to have both the hot and cold water pipe work re-run to suit the new application.  Note the electrical wiring was required to be relocated to suit the...