Account for works on site.
We have recently been asked to attend the above site as there was a report of faulty hot water.
We investigated and were able to identify that the tempering valve was faulty and needed to be replaced.
We supplied and installed 1 x new Tempering valve and made good the connection to the hot and cold water.
We tested and commissioned as per specifications. All works completed.